Dept. of Trans. PROGRESS Serial No. Contract No. 09-294-13-21 05-0S7504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 100% 05-SCR-1-4.0/4.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-09 GRANITEROCK,PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE, CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 348,811.84 210,015.03 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 348,811.84 210,015.03 5. Mobilization 6. Total Work Completed 348,811.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -34,881.18 -21,001.50 c. Reduction after 95% Comp. 9. Total pay to Contractor 313,930.66 189,013.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,013.53