Dept. of Trans. PROGRESS Serial No. Contract No. 15-112-13-49 05-0S7904 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 8% Location: Federal Project: 05-SLO-101-R21.6/R23.9 NHP-Q101(244) Progress payment No. 002 Payment period ending: 04-20-15 CALPORTLAND CONSTRUCTION P.O. BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 97,570.60 94,758.10 2. a. Extra Work 420,359.63 420,359.63 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 517,930.23 515,117.73 5. Mobilization 150,000.00 150,000.00 6. Total Work Completed 667,930.23 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 667,930.23 665,117.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 665,117.73