Dept. of Trans. PROGRESS Serial No. Contract No. 11-144-15-08 05-0S8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 53% 05-SB-1 Federal Project: 05-SB-101 NONE Progress payment No. 03 Payment period ending: 05-20-11 TRUESDELL CORPORATION OF CALIFORNIA INC 1310 W 23RD STREET TEMPE AZ 85282 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 387,694.30 21,578.35 2.a. Extra Work 5,184.94 5,184.94 b. Adjustment Comp. -250.00 -1,000.00 3. Materials on Hand 4. Earned Subject to Retention 392,629.24 25,763.29 5. Mobilization 48,329.50 0.00 6. Total Work Completed 440,958.74 7. Deductions -481.70 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 440,477.04 25,763.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,763.29