Dept. of Trans. PROGRESS Serial No. Contract No. 10-062-13-18 05-0S9504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 18% 05-MON-1-7.1/7.3 Federal Project: NONE Progress payment No. 01 Payment period ending: 03-03-10 WINSOR CONSTRUCTION INC 1022 SAN SIMEON CREEK RD CAMBRIA, CA 93428 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 219,986.52 219,986.52 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 219,986.52 219,986.52 5. Mobilization 6. Total Work Completed 219,986.52 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 219,986.52 219,986.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 219,986.52