Dept. of Trans. PROGRESS Serial No. Contract No. 16-145-14-18 05-0T5404 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 4% Location: Federal Project: 05-SCR-129-9.5/10.0 HSST-PG--(---) -----P129(16) Progress payment No. 004 Payment period ending: 05-20-16 GRANITE ROCK COMPANY 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 200,273.00 56,776.00 2. a. Extra Work 369.18 0.00 b. Adustment Comp. 3. Materials on Hand 10,731.87 0.00 4. Earned Subject to Retention 211,374.05 56,776.00 5. Mobilization 198,147.50 198,147.50 6. Total Work Completed 398,789.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 409,521.55 254,923.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 254,923.50