Dept. of Trans. PROGRESS Serial No. Contract No. 18-081-15-11 05-0T5404 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 92% Location: Federal Project: 05-SCR-129-9.5/10.0 HSST-PG--(---) -----P129(16) Progress payment No. 024 Payment period ending: 03-20-18 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,969,897.49 4,594.00 2. a. Extra Work 517,470.05 19,140.00 b. Adustment Comp. 105,422.78 -14,271.41 3. Materials on Hand 4. Earned Subject to Retention 4,592,790.32 9,462.59 5. Mobilization 396,295.00 0.00 6. Total Work Completed 4,989,085.32 7. Deductions -25,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,964,085.32 9,462.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,462.59