Dept. of Trans. PROGRESS Serial No. Contract No. 10-172-12-58 05-0T5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 63% 05-MON-1-225.0/229.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-20-10 JOHN MADONNA CONSTRUCTION CO PO BOX 5310 SAN LUIS OBISPO, CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 443,729.54 109,744.91 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 443,729.54 109,744.91 5. Mobilization 6. Total Work Completed 443,729.54 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 443,729.54 109,744.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 109,744.91