Dept. of Trans. PROGRESS Serial No. Contract No. 15-203-11-06 05-0T6404 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 31% Location: Federal Project: 05-SBT-25-18.8/19.5 HSST-P025(30) Progress payment No. 003 Payment period ending: 07-20-15 JOHN MADONNA CONSTRUCTION CO., INC. P.O. BOX 5310 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 642,287.83 452,914.53 2. a. Extra Work 41,383.14 35,113.46 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 683,670.97 488,027.99 5. Mobilization 153,187.50 32,250.00 6. Total Work Completed 836,858.47 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 836,858.47 520,277.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 520,277.99