Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-069-11-22 05-0T7604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-MON-1-R77.6 HSNH-P001(585) Progress payment No. 005 Payment period ending: 02-09-15 GRANITE CONSTRUCTION COMPANY 580 WEST BEACH STREET WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 422,319.62 0.00 2. a. Extra Work b. Adustment Comp. -5,903.25 -5,903.25 3. Materials on Hand 4. Earned Subject to Retention 416,416.37 -5,903.25 5. Mobilization 6. Total Work Completed 416,416.37 7. Deductions -28,056.37 35,237.25 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 388,360.00 29,334.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,334.00