Dept. of Trans. PROGRESS Serial No. Contract No. 06-326-11-37 05-129104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 24% 05-SCR-1-15.8/17.6 Federal Project: 05-SCR-17-0.1/0.7 ACNH-X087(28) ACBH-X087(28) NH-X087(28) Progress payment No. 08 Payment period ending: 11-20-06 PAVEX MYERS J V 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,202,188.97 1,603,604.10 2.a. Extra Work 811,624.54 153,951.80 b. Adjustment Comp. 266,903.00 266,903.00 3. Materials on Hand 1,305,986.28 424,257.28 4. Earned Subject to Retention 12,586,702.79 2,448,716.18 5. Mobilization 3,752,500.00 0.00 6. Total Work Completed 15,033,216.51 7. Deductions -30,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,309,202.79 2,448,716.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,448,716.18