Dept. of Trans. PROGRESS Serial No. Contract No. 10-263-10-14 05-129114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 90% 05-SCR-1-15.3/17.1 Federal Project: 05-SCR-17-0.1/0.7 NONE Progress payment No. 06 Payment period ending: 09-20-10 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 949014820 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 282,320.80 10,650.00 2.a. Extra Work b. Adjustment Comp. -7,654.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 274,666.30 10,650.00 5. Mobilization 65,550.00 0.00 6. Total Work Completed 340,216.30 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. -1,065.00 -1,065.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 338,151.30 9,585.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,585.00