Dept. of Trans. PROGRESS Serial No. Contract No. 12-298-09-22 05-1A2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 19% 05-SB-101-78.4/82.2 Federal Project: ACNH-Q101(216) Progress payment No. 05 Payment period ending: 10-20-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 575,066.75 15,350.00 2.a. Extra Work 6,663.09 6,663.09 b. Adjustment Comp. -9,213.57 -9,213.57 3. Materials on Hand 4. Earned Subject to Retention 572,516.27 12,799.52 5. Mobilization 50,000.00 0.00 6. Total Work Completed 622,516.27 7. Deductions -2,000.00 -500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 620,516.27 12,299.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,299.52