Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-014-14-15 05-1A3304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SB-166-55.1/70.6 STP-P166(32) Progress payment No. 005 Payment period ending: 12-09-15 GRANITE CONSTRUCTION COMPANY PO BOX 720 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,036,388.63 0.00 2. a. Extra Work 36,612.94 0.00 b. Adustment Comp. -35,103.92 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,037,897.65 0.00 5. Mobilization 289,404.00 0.00 6. Total Work Completed 3,327,301.65 7. Deductions -206,955.73 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,120,345.92 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00