Dept. of Trans. PROGRESS Serial No. Contract No. 14-203-13-07 05-1A3904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 17% 05-SB-101-84.1/90.9 Federal Project: NHP-Q101(241) Progress payment No. 01 Payment period ending: 07-20-14 PAPICH CONSTRUCTION CO. INC. PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 319,144.61 319,144.61 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 319,144.61 319,144.61 5. Mobilization 132,828.29 132,828.29 6. Total Work Completed 451,972.90 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 451,972.90 451,972.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 451,972.90