Dept. of Trans. PROGRESS Serial No. Contract No. 11-332-09-37 05-1A5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 4% 5% 05-MON-1-21.5/21.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 11-20-11 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ, CA 93428 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 222,470.09 222,470.09 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 222,470.09 222,470.09 5. Mobilization 6. Total Work Completed 222,470.09 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 222,470.09 222,470.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,470.09