Dept. of Trans. PROGRESS Serial No. Contract No. 14-352-13-52 05-1A6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 61% 05-SB-101-46.9/ .0 Federal Project: NHP-Q101(239) Progress payment No. 08 Payment period ending: 12-20-14 PRISM ENGINEERING INC 23953 SAKLAN RD HAYWARD CA 94545 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 853,369.50 4,005.00 2.a. Extra Work 53,667.04 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 907,036.54 4,005.00 5. Mobilization 6. Total Work Completed 907,036.54 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 907,036.54 4,005.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,005.00