Dept. of Trans. PROGRESS Serial No. Contract No. 13-085-07-30 05-1A6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 25% 05-MON-1-58.3/ .0 Federal Project: 05-MON-1-59.9/ .0 ACST-P19A(200) Progress payment No. 07 Payment period ending: 03-20-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,369,182.71 1,081,789.95 2.a. Extra Work 39,877.51 9,317.93 b. Adjustment Comp. 5,893.50 0.00 3. Materials on Hand 223,305.04 -275,312.00 4. Earned Subject to Retention 4,638,258.76 815,795.88 5. Mobilization 1,159,000.00 0.00 6. Total Work Completed 5,573,953.72 7. Deductions -125,823.74 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,671,435.02 815,795.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 815,795.88