Dept. of Trans. PROGRESS Serial No. Contract No. 13-235-13-15 05-1A6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 45% 05-MON-1-58.3/ .0 Federal Project: 05-MON-1-59.9/ .0 ACST-P19A(200) Progress payment No. 12 Payment period ending: 08-20-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,461,438.21 667,778.05 2.a. Extra Work 132,496.89 38,955.17 b. Adjustment Comp. 12,650.61 0.00 3. Materials on Hand 0.00 -137,656.00 4. Earned Subject to Retention 8,606,585.71 569,077.22 5. Mobilization 1,220,000.00 0.00 6. Total Work Completed 9,826,585.71 7. Deductions -132,446.05 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,694,139.66 569,077.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 569,077.22