Dept. of Trans. PROGRESS Serial No. Contract No. 16-026-16-34 05-1A7204 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 64% Location: Federal Project: 05-SB-101-21.0/27.1 NHP-Q101(262) Progress payment No. 007 Payment period ending: 01-20-16 GRANITE CONSTRUCTION COMPANY PO BOX 6744 SANTA BARBAA CA 93160 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,008,000.74 110,248.75 2. a. Extra Work 12,043.14 0.00 b. Adustment Comp. 60,000.00 0.00 3. Materials on Hand 348,542.94 -4,389.20 4. Earned Subject to Retention 1,428,586.82 105,859.55 5. Mobilization 576,805.50 0.00 6. Total Work Completed 1,656,849.38 7. Deductions -19,075.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,986,317.32 105,859.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,859.55