Dept. of Trans. PROGRESS Serial No. Contract No. 13-200-16-34 05-1A7904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 43% 05-SB-101-0.0/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-13 O'DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 404,350.32 246,050.22 2.a. Extra Work 1,666.72 1,666.72 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 406,017.04 247,716.94 5. Mobilization 65,000.00 3,250.00 6. Total Work Completed 471,017.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 471,017.04 250,966.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 250,966.94