Dept. of Trans. SEMI-FINAL Serial No. Contract No. 19-074-10-55 05-1C0904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-MON-68-15.0/T18.5 NHP-X053(29) 05-MON-101-R39.5/73.0 Progress payment No. 020 Payment period ending: 03-13-17 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,130,619.60 0.00 2. a. Extra Work 161,650.01 0.00 b. Adustment Comp. 179,792.96 6,537.56 3. Materials on Hand 4. Earned Subject to Retention 2,472,062.57 6,537.56 5. Mobilization 167,556.00 0.00 6. Total Work Completed 2,639,618.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,639,618.57 6,537.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,537.56