Dept. of Trans. PROGRESS Serial No. Contract No. 17-234-10-40 05-1C1104 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 81% Location: Federal Project: 05-SLO-101-12.4/29.7 NHP-Q101(302) Progress payment No. 006 Payment period ending: 08-20-17 SOUZA CONSTRUCTION INC PO BOX 3810 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 743,954.52 363,823.43 2. a. Extra Work 226.92 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 744,181.44 363,823.43 5. Mobilization 51,322.80 0.00 6. Total Work Completed 795,504.24 7. Deductions -5,000.00 56,066.06 8. a. Contract Retentions b. Unsatisfactory Retentions -36,382.34 -36,382.34 c. Reduction after 95% Comp. 9. Total pay to Contractor 754,121.90 383,507.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 383,507.15