Dept. of Trans. PROGRESS Serial No. Contract No. 16-081-09-47 05-1C1304 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 40% Location: Federal Project: 05-SLO-1-R12.6 NONE Progress payment No. 004 Payment period ending: 03-20-16 SOUZA CONSTRUCTION INC PO BOX 3810 SAN LUIS OBISPO CA 934033810 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 195,566.86 101,966.29 2. a. Extra Work 3,039.92 226.03 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 198,606.78 102,192.32 5. Mobilization 20,185.00 1,009.25 6. Total Work Completed 218,791.78 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 218,791.78 113,201.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 113,201.57