Dept. of Trans. PROGRESS Serial No. Contract No. 25-142-07-47 05-1C3604 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 42% Location: Federal Project: 05-SB-217-0.9/1.4 ACNH-P217(3) Progress payment No. 024 Payment period ending: 05-20-25 MCM CONSTRUCTION INC 6413 32ND ST NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,913,663.80 1,051,632.27 2. a. Extra Work 1,627,619.85 19,772.41 b. Adustment Comp. 55,218.89 0.00 3. Materials on Hand 981,244.02 58,489.12 4. Earned Subject to Retention 15,577,746.56 1,129,893.80 5. Mobilization 2,613,000.00 0.00 6. Total Work Completed 17,209,502.54 7. Deductions -22,035.28 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,168,711.28 1,129,893.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,129,893.80