Dept. of Trans. PROGRESS Serial No. Contract No. 19-203-15-35 05-1C3704 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 21% Location: Federal Project: 05-SLO-101-16.4 B1NH-Q101(340) Progress payment No. 003 Payment period ending: 07-20-19 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 748,847.00 597,992.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 170,772.48 -47,230.98 4. Earned Subject to Retention 919,619.48 550,761.02 5. Mobilization 222,300.00 46,800.00 6. Total Work Completed 971,147.00 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,139,919.48 597,561.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 597,561.02