Dept. of Trans. PROGRESS Serial No. Contract No. 20-079-12-09 05-1C3704 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 93% Location: Federal Project: 05-SLO-101-16.4 B1NH-Q101(340) Progress payment No. 011 Payment period ending: 03-20-20 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 B VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,212,657.20 1,260.00 2. a. Extra Work 21,917.66 0.00 b. Adustment Comp. -159,464.47 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,075,110.39 1,260.00 5. Mobilization 234,000.00 0.00 6. Total Work Completed 2,309,110.39 7. Deductions -30,000.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,279,110.39 8,260.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,260.00