Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-12-33 05-1C4104 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 38% Location: Federal Project: 05-SB-154-R2.6 NONE Progress payment No. 016 Payment period ending: 09-20-24 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,252,338.25 2,480.25 2. a. Extra Work 51,853.33 0.00 b. Adustment Comp. -3,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,301,191.58 2,480.25 5. Mobilization 387,500.00 0.00 6. Total Work Completed 3,688,691.58 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,688,691.58 12,480.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,480.25