Dept. of Trans. PROGRESS Serial No. Contract No. 15-022-14-34 05-1C4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 100% 05-SB-101-12.9/R14.0 Federal Project: NONE Progress payment No. 18 Payment period ending: 01-20-15 SPIESS CONSTRUCTION CO INC P O BOX 2849 SANTA MARIA CA 93457 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 601,085.00 4,320.00 2.a. Extra Work 41,035.26 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 642,120.26 4,320.00 5. Mobilization 17,000.00 0.00 6. Total Work Completed 659,120.26 7. Deductions -1,080.00 -1,080.00 8. a.Contract Retentions b. Unsatisfactory Prog. -432.00 -432.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 657,608.26 2,808.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,808.00