Dept. of Trans. PROGRESS Serial No. Contract No. 16-263-14-54 05-1C4304 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 05-SB-101-12.9/R14.0 NONE Progress payment No. 038 Payment period ending: 09-20-16 SPIESS CONSTRUCTION CO INC PO BOX 2849 SANTA MARIA CA 93457 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 695,765.00 4,680.00 2. a. Extra Work 41,035.26 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 736,800.26 4,680.00 5. Mobilization 17,000.00 0.00 6. Total Work Completed 753,800.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 753,800.26 4,680.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,680.00