Dept. of Trans. PROGRESS Serial No. Contract No. 16-342-10-42 05-1C4304 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 05-SB-101-12.9/R14.0 NONE Progress payment No. 040 Payment period ending: 11-20-16 SPIESS CONSTRUCTION CO INC PO BOX 2849 SANTA MARIA CA 93457 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 715,481.00 4,680.00 2. a. Extra Work 41,035.26 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 756,516.26 4,680.00 5. Mobilization 17,000.00 0.00 6. Total Work Completed 773,516.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 773,516.26 4,680.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,680.00