Dept. of Trans. PROGRESS Serial No. Contract No. 12-205-14-21 05-1C5604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 0% 05-SB-101-47.3 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-18-12 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE, CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 262,973.56 262,973.56 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 262,973.56 262,973.56 5. Mobilization 6. Total Work Completed 262,973.56 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 262,973.56 262,973.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 262,973.56