Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-024-17-14 05-1C6704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SCR-17-0.2/0.5 HSNH-P017(115) Progress payment No. 028 Payment period ending: 12-16-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,466,864.74 19,337.30 2. a. Extra Work 1,045,841.31 0.00 b. Adustment Comp. 340,412.30 -11,824.87 3. Materials on Hand 4. Earned Subject to Retention 4,853,118.35 7,512.43 5. Mobilization 443,000.00 0.00 6. Total Work Completed 5,296,118.35 7. Deductions -21,600.63 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,274,517.72 27,512.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,512.43