Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-177-08-21 05-1C8004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 05-SLO-101-37.7 NONE Progress payment No. 003 Payment period ending: 06-10-15 SOUZA CONSTRUCTION INC P.O. BOX 3810 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 254,930.41 6,568.50 2. a. Extra Work 5,604.61 3,454.49 b. Adustment Comp. 29,906.95 29,906.95 3. Materials on Hand 4. Earned Subject to Retention 290,441.97 39,929.94 5. Mobilization 13,092.50 0.00 6. Total Work Completed 303,534.47 7. Deductions -15,012.84 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 288,521.63 29,929.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,929.94