Dept. of Trans. PROGRESS Serial No. Contract No. 17-234-10-41 05-1C8304 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 69% Location: Federal Project: 05-SB-154-R5.9/22.9 STP-P154(22) Progress payment No. 013 Payment period ending: 08-20-17 CALPORTLAND CONSTRUCTION PO BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,325,665.63 282,409.27 2. a. Extra Work 397,187.98 113,331.20 b. Adustment Comp. 111,656.74 105,346.34 3. Materials on Hand 185,571.61 19,370.61 4. Earned Subject to Retention 10,020,081.96 520,457.42 5. Mobilization 812,130.00 0.00 6. Total Work Completed 10,646,640.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,832,211.96 520,457.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 520,457.42