Dept. of Trans. PROGRESS Serial No. Contract No. 20-023-13-44 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 33% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 011 Payment period ending: 01-20-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,735,731.17 382,806.12 2. a. Extra Work 244,533.02 90,032.37 b. Adustment Comp. -33,539.30 0.00 3. Materials on Hand 1,413,976.00 225,696.00 4. Earned Subject to Retention 13,360,700.89 698,534.49 5. Mobilization 2,033,000.00 0.00 6. Total Work Completed 13,979,724.89 7. Deductions -110,574.34 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,283,126.55 698,534.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 698,534.49