Dept. of Trans. PROGRESS Serial No. Contract No. 20-055-13-39 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 28% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 012 Payment period ending: 02-20-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,672,206.75 1,936,475.58 2. a. Extra Work 248,609.29 4,076.27 b. Adustment Comp. -33,539.30 0.00 3. Materials on Hand 1,891,729.00 477,753.00 4. Earned Subject to Retention 15,779,005.74 2,418,304.85 5. Mobilization 2,033,000.00 0.00 6. Total Work Completed 15,920,276.74 7. Deductions -111,574.34 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,700,431.40 2,417,304.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,417,304.85