Dept. of Trans. PROGRESS Serial No. Contract No. 20-175-12-35 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 32% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 016 Payment period ending: 06-20-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,490,976.79 2,570,035.59 2. a. Extra Work 270,868.33 9,661.44 b. Adustment Comp. -10,647.30 0.00 3. Materials on Hand 2,131,618.00 0.00 4. Earned Subject to Retention 21,882,815.82 2,579,697.03 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 21,891,197.82 7. Deductions -115,931.34 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,906,884.48 2,579,697.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,579,697.03