Dept. of Trans. PROGRESS Serial No. Contract No. 20-266-21-06 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 41% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 020 Payment period ending: 09-20-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,155,431.31 2,010,549.25 2. a. Extra Work 476,235.51 44,193.66 b. Adustment Comp. -10,647.30 0.00 3. Materials on Hand 2,121,459.00 24,531.00 4. Earned Subject to Retention 26,742,478.52 2,079,273.91 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 26,761,019.52 7. Deductions -85,058.82 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,797,419.70 2,079,273.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,079,273.91