Dept. of Trans. PROGRESS Serial No. Contract No. 20-300-21-38 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 45% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 021 Payment period ending: 10-20-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,783,562.67 2,628,131.34 2. a. Extra Work 522,722.96 46,487.45 b. Adustment Comp. -10,647.30 0.00 3. Materials on Hand 38,279.35 -2,083,179.65 4. Earned Subject to Retention 27,333,917.68 591,439.14 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 29,435,638.33 7. Deductions -90,058.82 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,383,858.86 586,439.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 586,439.14