Dept. of Trans. PROGRESS Serial No. Contract No. 20-328-19-33 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 49% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 022 Payment period ending: 11-20-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,237,684.83 454,122.16 2. a. Extra Work 544,734.14 22,011.18 b. Adustment Comp. -10,647.30 0.00 3. Materials on Hand 38,279.35 0.00 4. Earned Subject to Retention 27,810,051.02 476,133.34 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 29,911,771.67 7. Deductions -90,058.82 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,859,992.20 476,133.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 476,133.34