Dept. of Trans. PROGRESS Serial No. Contract No. 20-363-12-00 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 53% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 023 Payment period ending: 12-20-20 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,453,918.68 216,233.85 2. a. Extra Work 544,734.14 0.00 b. Adustment Comp. -10,647.30 0.00 3. Materials on Hand 252,417.12 214,137.77 4. Earned Subject to Retention 28,240,422.64 430,371.62 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 30,128,005.52 7. Deductions -90,058.82 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,290,363.82 430,371.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 430,371.62