Dept. of Trans. PROGRESS Serial No. Contract No. 21-026-21-19 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 52% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 024 Payment period ending: 01-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,586,379.76 132,461.07 2. a. Extra Work 544,734.14 0.00 b. Adustment Comp. -10,647.30 0.00 3. Materials on Hand 372,351.00 119,933.88 4. Earned Subject to Retention 28,492,817.60 252,394.95 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 30,260,466.60 7. Deductions -85,058.82 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,547,758.78 257,394.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 257,394.95