Dept. of Trans. PROGRESS Serial No. Contract No. 21-236-15-49 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 69% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 032 Payment period ending: 08-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,414,639.21 113,805.21 2. a. Extra Work 1,614,424.32 445,266.23 b. Adustment Comp. -6,219.70 -75,220.05 3. Materials on Hand 4. Earned Subject to Retention 36,022,843.83 483,851.39 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 38,162,843.83 7. Deductions -632,037.05 -154,380.16 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,530,806.78 329,471.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 329,471.23