Dept. of Trans. PROGRESS Serial No. Contract No. 21-264-17-52 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 74% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 033 Payment period ending: 09-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,197,132.61 -217,506.56 2. a. Extra Work 1,795,301.24 180,876.92 b. Adustment Comp. -363,817.77 -357,598.07 3. Materials on Hand 4. Earned Subject to Retention 35,628,616.08 -394,227.71 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 37,768,616.08 7. Deductions -132,438.98 499,598.07 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,636,177.10 105,370.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,370.36