Dept. of Trans. PROGRESS Serial No. Contract No. 22-026-12-06 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 92% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 036 Payment period ending: 01-20-22 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,126,067.34 152.28 2. a. Extra Work 2,221,948.94 66,459.25 b. Adustment Comp. -97,352.51 10,591.00 3. Materials on Hand 4. Earned Subject to Retention 36,250,663.77 77,202.53 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 38,390,663.77 7. Deductions -248,332.43 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,142,331.34 77,202.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,202.53