Dept. of Trans. PROGRESS Serial No. Contract No. 22-115-15-27 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 86% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 039 Payment period ending: 04-20-22 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,126,067.34 0.00 2. a. Extra Work 2,544,376.83 13,353.92 b. Adustment Comp. -171,973.91 -74,621.40 3. Materials on Hand 4. Earned Subject to Retention 36,498,470.26 -61,267.48 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 38,638,470.26 7. Deductions -137,438.98 110,893.45 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,501,031.28 49,625.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,625.97