Dept. of Trans. PROGRESS Serial No. Contract No. 22-171-11-41 05-1C8904 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 94% Location: Federal Project: 05-MON-101-87.3/R91.5 B1NH-Q101(342) Progress payment No. 040 Payment period ending: 06-20-22 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,253,435.51 127,368.17 2. a. Extra Work 2,581,338.55 36,961.72 b. Adustment Comp. -171,973.91 0.00 3. Materials on Hand 4. Earned Subject to Retention 36,662,800.15 164,329.89 5. Mobilization 2,140,000.00 0.00 6. Total Work Completed 38,802,800.15 7. Deductions -137,438.98 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,665,361.17 164,329.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 164,329.89