Dept. of Trans. PROGRESS Serial No. Contract No. 14-170-10-51 05-1C9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 89% 05-SCR-1-R1.0/R15.8 Federal Project: 05-MON-1-R75.7/102.0 NONE 05-MON-68-R4.0/ .0 Progress payment No. 03 Payment period ending: 06-20-14 AMERICAN CIVIL CONSTRUCTORS WEST COAST, INC. 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 415,218.63 64,808.25 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 415,218.63 64,808.25 5. Mobilization 60,500.00 0.00 6. Total Work Completed 475,718.63 7. Deductions -562.64 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 475,155.99 64,808.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 64,808.25