Dept. of Trans. PROGRESS Serial No. Contract No. 16-027-13-14 05-1C9404 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 100% Location: Federal Project: 05-MON-1-11.7/43.1 NONE Progress payment No. 005 Payment period ending: 01-20-16 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 547,610.12 0.00 2. a. Extra Work 228,255.50 224,405.50 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 775,865.62 224,405.50 5. Mobilization 113,000.00 0.00 6. Total Work Completed 888,865.62 7. Deductions -41,397.44 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 847,468.18 214,405.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 214,405.50