Dept. of Trans. PROGRESS Serial No. Contract No. 21-026-21-48 05-1E0004 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 34% Location: Federal Project: 05-SB-101-R56.2/58.0 NONE Progress payment No. 003 Payment period ending: 01-20-21 LANDSCAPE SUPPORT SERVICES INC 12610 SATICOY ST SOUTH N HOLLYWOOD CA 91605 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 715,330.26 227,574.85 2. a. Extra Work 12,722.81 12,722.81 b. Adustment Comp. 3. Materials on Hand 81,317.90 -27,520.08 4. Earned Subject to Retention 809,370.97 212,777.58 5. Mobilization 174,705.00 0.00 6. Total Work Completed 902,758.07 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 974,075.97 202,777.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,777.58